Week 5

Main door door frame removed. AHU door frame pending EM lock confirmation.
week5-1.PNG
Metal work for glass support and metal frame work in progress.
week5-2.PNG
week5-3.PNG
Embedded conduit in partition completed, partition wall work in progress.
week5-4.PNG
week5-5.PNG
Chilled water pipe installation work in progress.
week5-6.PNG
week5-7.PNG
Fresh air duct work in progress.
week5-8.PNG
week5-9.PNG
High level trunking, conduit and wiring work in progress.
week5-10.PNG
week5-11.PNG
Embedded SOB & wiring work in progress.
week5-12.PNG
week5-13.PNG