Renovation progress

Share        

Week 4

brick wall

Brickwall for AHU room completed; Pipe sleeves for penetration provided.
week4 - 1.PNG

week4 - 2.PNG

 partition work

Partition wall work in progress.

week4 - 3.PNG

week4 - 4.PNG

week4 - 5.PNG

week4 - 6.PNG

week4 - 7.PNG

week4 - 8.PNG

 Electrical work

Hacking of additional SOB box work in progress.

week4 - 9.PNG

week4 - 10.PNG

 High level trunking, conduit and wiring work in progress.
 
week4 - 11.PNG
week4 - 12.PNG

 ACMV Work

Chilled water pipe & fresh air duct work in progress.

week4 - 13.PNG
week4 - 14.PNG
 Fresh air intake duct work in progress, PID duct for PDV completed.

week4 - 15.PNG

week4 - 16.PNG