Renovation progress

Share        

Week 7

Location of TV pending confirmation, area on hold pending further instruction.


Putty of partition wall work in progress.

Ceiling grid work in progress.
week7-5.PNG
week7-6.PNG
Plumbing piping work completed; new floor waste completed.
week7-7.PNG
week7-8.PNG
ACMV Chilled water main pipe completed; BMS installation in progress.
week7-9.PNG
week7-10.PNG
Sprinkler branch pipe completed; pending Ceiling grid to final fitting.
week7-11.PNG
week7-12.PNG
Water proofing completed; ponding test completed with satisfactory
week7-13.PNG