Renovation progress

Share        

Week 6

Partition beside main entrance pending confirmation to proceed.
week6-1.PNG
week6-2.PNG
Metal work for glass support completed.
week6-3.PNG

Partition work in progress.
week6-5.PNG
week6-6.PNG
Ceiling Grid work in progress. Plumbing & sanitary work in progress.
week6-7.PNG
week6-8.PNG
 ACMV Chilled water main pipe completed. 
week6-9.PNG
week6-10.PNG
Fire Damper installed.
week6-11.PNG