Renovation progress

Share        

Week 11

Main Entrance Signage pending further review. Main Entrance Feature wall elevation of door area pending design.
week11-1.PNG
week11-2.PNG
EM Lock for main door installed.
week11-3.PNG
week11-4.PNG
Carpentry work/ customized furniture in progress.
week11-5.PNG
week11-6.PNG
Linear bar grille installation work in progress.
week11-7.PNG
week11-8.PNG
Switches and power point installation work in progress.
week11-9.PNG
week11-10.PNG
Exit light installation completed. Fire rated door at AHU Room completed.    
week11-11.PNG
week11-12.PNG