Renovation progress

Share        

Week 10

Carpet and Vinyl Floor finishes completed.
week10-1.PNG
week10-2.PNG
Ceiling and wall painting completed.
week10-3.PNG
week10-4.PNG
Glass & metal feature frame installation in progress.
week10-5.PNG
week10-6.PNG
Ceiling spray painting completed. (Open Ceiling).
week10-7.PNG
week10-8.PNG
Lighting, switches and power point installation work in progress.
week10-9.PNG
week10-10.PNG
Electrical DB Installed. Exit light installation work in progress.
week10-11.PNG
week10-12.PNG
Control panel installed. AHU delivered and installation in progress.      
week10-13.PNG
week10-14.PNG